Construction of high Rise tower office Complex at New Delhi for standing Conference of Public Enterprises (SCOPE). This Complex consists of two basements and three floors of 100 m diameter and two tower blocks 18 and 13 storeyes respectively having a total builtup area if 1,10,000 m2.
Consturction Chemical Mentioned below were used:
CEMWET SP-1, Super Plasticizer for
flowering Concrete.
BOND-AID for bonding and Repair works.
CURE WELL-WB for curing of concrete.
|
CEMWET ACC, Accelerator for Precast elements.
ASIAN MRA for Precast and Sturctural concrete.
POLYCOAT-SRP, Water-Proffing Coating System. |